Wednesday, March 12, 2014

Update




Construction and renovation continues in the 1965 portion of the building.  We have 3 months left for this phase to be finished!! and then we will start Phase 4.

-Structural Steel is in.
-Block infill and sheet rock infills are being worked out in the      most creative way we can. 
-Brunel Roofing has started roofing the kitchen and new cafeteria.
-All demo in kitchen is done and new plumbing and trenches in the exiting slab have been taken care of. Kitchen infill in slab and new slab will be pour tomorrow.
-Andy Shapiro is on site today checking air Leakage.  
-Sprinkler for this area has been rough in to.

The good news is the paint issue in the gym has been resolved!  The gym had a lot of work done over vacation and it is re-painted now.  Here are some pictures of them striping the paint and prepping for the new paint.






PLEASE EMAIL US IF YOU HAVE ANY QUESTIONS

diazsmith.flor@gmail.com