CONSTRUCTION PHASES


Phase I-II:  June 24th – December, 2013
During Phase I, the contractors will complete the expansion of the building, which will include two new classrooms, the art and music room, foreign language office, additional storage, and new bathrooms.  There will be underground storage for grounds equipment and our fire pump in this part of the building as well.  In addition, the existing gym will be renovated in the summer of 2013.

Phase III: January, 2014 – June 23, 2014
A section of the school from the existing pre-k classroom down to K/1 exit near the parent drop off, will be relocated to the new wing.  During Phase III, the contractors will build the new library, the pre-k classroom, and the “admin suite,” which includes guidance, health, occupational therapy, a conference room, staff room, and the principals’ office.  The kitchen and new cafeteria will be built in the latter part of Phase III. This will include asbestos abatement, that will happen in February school Break.  Town Meeting will be at U32 this year.

Phase IV: June, 2014 – August, 2014
During Phase III, the contractors will complete the work started in Phase II and III, as well as all other work in the existing building. That needs to be linked to the entire building.   heating and ventilation, window, insulation, lighting fixtures, etc.  The existing library will become two primary classrooms, and the existing bathrooms will be renovated.  This work will be completed in August, 2014.
Work to the exterior of the building will begin in the summer of 2013, and will conclude the summer of 2014. 