Wednesday, December 11, 2013







The Renovation is on time, they will be ready for our big move on December 23rd.
Taping is completed they are finishing painting and installing cabinets on all the new spaces.  The new concrete slab has been grind and polish.  They are tiling the new bathrooms today.
A lot of testing is going on this week and next week they will try to keep the noise and disruption to a minimum for students. (Fire Alarm, generator, fire pump, etc)
Ceilings are being hanged now and acoustical work is happening on the new Music Room.
On December 19th the State will come to do a final walk and give us our Occupancy Permit for the new addition.
Teachers and Administrator now on the 1965 wing of the building will be moving to the new addition to give room to work on Phase 3 to start.

We will be posting more details soon stayed tuned!  



NEW ART ROOM STORAGE



 ASBESTOS REMOVAL UPDATE BELLOW.



ASBESTOS REMOVAL UPDATE

Please be advised that asbestos removal work will be performed at East Montpelier Elementary School between December 24, 2013 and January 17, 2014.
The work will be conducted in the 1965 building section (administration area, east classrooms and etc.).  The asbestos-containing materials scheduled for removal are vinyl floor tiles, adhesive on mopboards and vinyl floor sheeting.  The asbestos removal areas will be isolated from the rest of the school building by a sealed, negative air pressure containment.  Each entrance leading the asbestos removal areas will be demarcated with signs that read, “Danger Asbestos” to warn people to keep out of these areas.
The abatement work will be conducted by Techtron Environmental from Essex Jct., Vermont.  Techtron is fully licensed and accredited as an asbestos abatement contractor by the Vermont Department of Health and the US Environmental Protection Agency respectively.  
The asbestos removal activities will be monitored by Crothers Environmental Group (CEG) out of Morrisville, Vermont.   CEG is an independent consulting company with absolutely no monetary affiliation with the asbestos removal contractor.   CEG is fully licensed and accredited as an asbestos consulting entity by the VDOH and the USEPA respectively.   CEG is tasked with ensuring that containment barriers are constructed properly before any asbestos removal activities begin.  CEG will also be collecting asbestos air samples before, during and after the work. In addition, CEG will conduct random compliance inspections of the asbestos removal contractor’s work practices.

PLEASE POST A COMMENT OR EMAIL US YOUR QUESTIONS.