Friday, February 28, 2014


Construction is moving quickly on Phase III

The kitchen is now close but do not worry breakfast and lunch will be served at school!!  Please visit the school webpage for the lunch menu in March.

Activities at School this week:

Kitchen asbestos abetment is happening now during break.
All demo is done in the east section of the 1965 area of the school.  From the temporary parking look to the gym area.
Trenches for plumbing are now closed.
Interior framming is going in now.
No surprises in storm and sewer lines.
Roof might be going on by the end of the week.
Stripping paint in the gym to re-paint.