Wednesday, April 30, 2014

Update




  1. Kitchen hood is in and the tile is in the kitchen!  Beautiful new quarry tile is in and ready to get grout.
  2. They are installing marmoleum in the server room and will start the cafeteria room this week.  We are going to heat a little the 1965 wing to make sure we keep the area at 55 F to satisfy our flooring warranty.
  3. Library Addition is framed and insulated.
  4. They continue to paint and work on the ceilings.
  5. Side walks are starting to go in and the south egress path is on the beginning stages.
  6. Time is of essence and the clock is running for our move on May 23!!



We had a great Oversight Committee Meeting today and had a walk through the construction.

We continue to work on the Pond issue and make sure we keep updating our Capital plan as we get owners manuals from the Contractor.

Thank you for all your time for the Committee!

Rob Chickering, Albert Petrella, Alice Angeny, Mike Duane, Alicia Lyford and Bill Ford



If you have any questions don't hesitate to call or email,
Alica alyford@u32.org
Flor diazsmith.flor@gmail.com

thank you for your support!



Respectfully

Flor


Wednesday, April 23, 2014

Update April 23,2014







They are full guns out in the addition! (Contractor language!)
First coat of paint in the new offices, library and cafeteria.
They are working on the library addition floors now and the entry way recess matt slabs.
The Stage Curtain was hanged yesterday.
We did some testing on the temporary parking area today, were we have some heaving from frost.
We continue to work on the final update for the Fire Water Pond.
The new kitchen equipment is on site.
The new marmoleum flooring will start to be installed this week.
The Structural engineer came to review the structure in Phase III and he was happy with everything.
The Beam bearing was reviewed and he will send us a site visit report.








New cafeteria

glass windows from hallway tto cafeteria




New Skylight!

look who is supervising the job after school!

 cafeteria with the new green and mayan gold on the walls!
looking at the time capsule, it will be on the library side wall as you enter the building.

sketches on site to install the metal box for the time capsule



Thank you Wright and Morrisey and Truex Cullins for all your hard work!!
Thank you Bill Ford too!


Thank you to you East Montpelier for your support and your patience!!

Monday, April 7, 2014

UPDATE



Wright and Morrissey has accepted the early substantial completion on Phase III on May 23, 2024!!
EMES Staff affected by this move will vacate the six classrooms on the West end of the 1965 addition. Asbestos abatement will start of May 27, 2014 for no more that 10 days.

On the site they are done installing new windows on the Phase III section.  They continue to finalize the roofing in the 1965 part of the School and they are busy finalizing the library framing and roof structure.
The New Cafeteria is all framed and closed in.  Plumbing inspection is done and now they are finalizing electrical, blocking and in some areas they are putting up the Sheet Rock!!  It is moving along fast and on schedule!!

Getting in an out of the drop off circle and parking is still hard so we appreciate your patience and remember it is temporary.   Most kids have taken a tour of the building and are enjoying seeing the progress.

The Oversight Committee is meeting twice a month every other Wednesday at 8:30 am and the main goal of the Committee is to make sure more people can be informed of the progress and can share with their neighbors and friends.  The Committee is also working on the Capital Plan with Todd's input.

If you have any questions please don't hesitate to post them in this blog, email diazsmith.flor@gmail.com or Alyford@U32.org or call the School.