UPDATE OVERSIGHT + FACILITIES
We are right on schedule!
The 1965 wing rooms are 95% finish, they are waiting for some window sills but other than that they are done.
Bill Ford and Dan are going to start the punch list for that space on August 6th.
The 1989 wing 3 rooms are completed with flooring and the we have 7 painters working in today.
Almost all of the Landscape is done! If you drive by take a look it looks great.
A lot is happening at the same time but all work is flowing and staying on schedule.
The pond work has started and we are still waiting for the shed price and preschool fence. These 3 items will be finished after the completion date.
Commissioning is happening on 4th and 7th with John Penny. All subs are ready for this to happen and have coordinated the date.
What is commissioning?
We are testing all the systems and components that were designed and spec by our Architect and Engineers. They make sure all of the systems have been installed correctly and tested so they are operating properly.
SOME PHOTOS: