Wednesday, July 30, 2014



UPDATE OVERSIGHT + FACILITIES


We are right on schedule!  

The 1965 wing rooms are 95% finish, they are waiting for some window sills but other than that they are done.  

Bill Ford and Dan are going to start the punch list for that space on August 6th.

The 1989 wing 3 rooms are completed with flooring and the we have 7 painters working in today.

Almost all of the Landscape is done!  If you drive by take a look it looks great.

A lot is happening at the same time but all work is flowing and staying on schedule.

The pond work has started and we are still waiting for the shed price and preschool fence.  These 3 items will be finished after the completion date.  

Commissioning is happening on 4th and 7th with John Penny. All subs are ready for this to happen and have coordinated the date. 

What is commissioning?

We are testing all the systems and components that were designed and spec  by our Architect and Engineers.  They make sure all of the systems have been installed correctly and tested so they are operating properly.  


SOME PHOTOS:










Wednesday, July 16, 2014

Update on Construction


Update Oversight and Facilities + Schedule



The Oversight Committee had a meeting today and we gave them an update on the Schedule and the Pond.

We reviewed the Schedule
We made it clear that the site subcontractor filing for Chapter 11 doesn't affect finishing the Site work and getting the pond done.
A new day for Commissioning of all systems is on the works, John Penny will be back when Control Tech and Brownell is ready.


Schedule this week:

Sheet rocking windows still going on.  Metal bending this morning for the rest of the flashing on windows.
Rough-in inspections for both the rest of 65 and 89 are done.
Moisture mitigation in the rest of the building is done we are finishing the corridors in the res of 1965 area.
We are putting flooring down in the classrooms that are ready in 1965.
They will be done sheet rocking this week.

The new door into the gym going in:






Wednesday, July 9, 2014



We are  currently on schedule!
The progress list for this week includes:

New American Elm's have been planted in the front and look beautiful.
They are working on sandblasting
Strong push all past week for doing all the roughing in.
They continue to work in the 65 addition suffits and tapping is going on.
Electrical Inspector was here to look at all the rough in.
The pond is starting on Monday and Wright and Morrisey is doing it with his own staff.
We meausure for a couple of new shades in the conference room and the reception window area.

Ady Shapiro was here and did a door blower test and was happy with all the work.

Commissioning is behind a little bit and we were not completely ready for John Penny last week.

bushes in

Trees ready to be planted












Monday, July 7, 2014







Update Oversight + Facilities



We had an Oversight Committee Meeting today July 2, 2014; Marty Miller, Alice Angney, Albert Petrella, Alicia Lyford were present.

Here are some high ights:


Don Marsh, Bill Ford, Strummer and Flor walked the pond site and also staked the proposed Garage site in the upper parking lot.  We will need a zoning permit for the garage, the hearing will be on August 5th.  

Alice suggested we might want to add a little stretch of side walk to link the side walk by the temporary parking lot




The temporary wall  in the music room is down and the carpet is in good shape not much fixing then.

Masonary filling the door openings is starting this week too.  The gym door has been taken down and the new door with sidelights is going in now.

Roof  opening in the learning center for the new skylight will be in this week too.

Landscape is going in little by little..  shrubs will come in at least some of them this week.

Andy is doing his walk through tomorrow to make sure air barrier is all