Wednesday, July 16, 2014

Update on Construction


Update Oversight and Facilities + Schedule



The Oversight Committee had a meeting today and we gave them an update on the Schedule and the Pond.

We reviewed the Schedule
We made it clear that the site subcontractor filing for Chapter 11 doesn't affect finishing the Site work and getting the pond done.
A new day for Commissioning of all systems is on the works, John Penny will be back when Control Tech and Brownell is ready.


Schedule this week:

Sheet rocking windows still going on.  Metal bending this morning for the rest of the flashing on windows.
Rough-in inspections for both the rest of 65 and 89 are done.
Moisture mitigation in the rest of the building is done we are finishing the corridors in the res of 1965 area.
We are putting flooring down in the classrooms that are ready in 1965.
They will be done sheet rocking this week.

The new door into the gym going in: