Wednesday, April 30, 2014

Update




  1. Kitchen hood is in and the tile is in the kitchen!  Beautiful new quarry tile is in and ready to get grout.
  2. They are installing marmoleum in the server room and will start the cafeteria room this week.  We are going to heat a little the 1965 wing to make sure we keep the area at 55 F to satisfy our flooring warranty.
  3. Library Addition is framed and insulated.
  4. They continue to paint and work on the ceilings.
  5. Side walks are starting to go in and the south egress path is on the beginning stages.
  6. Time is of essence and the clock is running for our move on May 23!!



We had a great Oversight Committee Meeting today and had a walk through the construction.

We continue to work on the Pond issue and make sure we keep updating our Capital plan as we get owners manuals from the Contractor.

Thank you for all your time for the Committee!

Rob Chickering, Albert Petrella, Alice Angeny, Mike Duane, Alicia Lyford and Bill Ford



If you have any questions don't hesitate to call or email,
Alica alyford@u32.org
Flor diazsmith.flor@gmail.com

thank you for your support!



Respectfully

Flor


No comments:

Post a Comment