We are busy at School getting ready for School to start on August 27th!!! The first few days kids are back at school we will be installing the flooring on the gym and getting it ready for kids to use it.
Please read the letter from Marion with details about the bag lunch menu for the first few days of school. Here is a paragraph from her letter:
"During the first week of school, the gym floor will be installed. Given this, we will be serving lunch/breakfast from the staff room and will provide a menu that can accommodate the facility. On Tuesday through Friday, bag lunches will be served; the menu is included in the first day packets. In advance, Tuesday’s bag lunch is a ham and cheese sandwich, fruit, veggie sticks and a choice of milk. Wednesday’s bag lunch is a turkey-cheese wrap, veggie sticks, fruit and choice of milk."
Strummer and his team from Wright and Morrissey are working hard to move fences and get the construction site ready and safe for kids to be at School. Please remember that the date of completion for this project is August 2014 so we have 12 months left of construction. We appreciate your understanding and we apologize for any inconvenience.
August 19,2013 to August 25,2013 Construction Activities for East Montpelier Elementary School
Gym Interior work
Finish Paint
Gym Floor Prep
Install Gym Equipment
East Elevation
Finish Gravel
Pave short term parking
South Elevation
Box cut Bus loop
Install gravel
Pave Parent drop off and Bus loop
Place concrete entrance
Form and place concrete for new South addition.
Build a new lay down area.