Construction schedule for:


September 23,2013 to September 29,2013 

  • Box cut existing road at short term parking and install road fabric and12”compacted crush gravel 6” of crush stone.
  • Extend culverts and swales at the bus loops & parents drop off entrances.
  • Install conduits and light poles bases front entrances.

  • Demo existing boiler
  • Start framing south addition.
  • Set misc. structural steel for south addition.
  • Mechanical & Electrical rough in the south addition.