We had a great assembly at school, kids looked at the renovated gym for the first time on Monday Sep 9th!!  It is not finished, we are waiting on acoustic panels, flooring on the stage and bleachers.  We are on schedule to have it ready for basketball season so stay tuned.  Here is the Schedule of Activities at School for the next two weeks:


    Activities for week of Sept.9,2013 to Sept.20,2013

                     Backfill south addition
                     Excavate for under slab mechanical piping and electrical.
                     Set structural steel for the south addition.
                     Prep for slab on deck and slab on grade.
                     Place slabs on deck and grade.
                     Start light gage framing for south addition.
                     Install swales along Vincents Flats Rd.
                     Set bar joists and metal deck.
                     Start interior electrical rough in.