Countdown to the 23rd temporary move is on!!
On Friday we will be moving all day and our new space we will be almost done. We will occupy the space for 3 weeks to allow them to get a head start on Phase IV.

The kitchen will be moved but won't be on full operation until the start of next school year.

Egress will be checked tomorrow with fire alarm, Mechanical will be running, fire extinguishers will be up.

We won't be using the temporary parking lot for now to let the contractor keep using it and keep the project going.

Paint is almost all done! 

The toilet partitions are in.

Window sill are in!

The ceilings won't be in until the end so we can keep working the cables into Phase IV.

The preschool class is done and will be used temporary for 3 weeks by Mr. Willard's class.

Here are a few pictures more to come!

Thank you Wright and Morrisey!!
Thank you TruexCullins!!
Thank you Bill Ford!!



hall way

 staff mail room