Wednesday, May 14, 2014








  1. Site works is still working on the side walks and exterior paths.
  2. Case work is going in the new addition.
  3. Painting is still going on all around the Phase III area it is looking great.
  4. Marmoleum floors are going in the circles look beautiful.
  5. We are on schedule for substantial completion.
  6. Andy Shapiro has walked the construction and his notes have been reviewed we need to add one insulated panel above one door.
  7. We will try do a preliminary punch list for phase III on May 21st
  8. The New gym door will be installed in the summer and will be to the side of the door for this preliminary move.
  9. The time capsule body is in the front will be in before the School year starts!
  10. We are working on furniture layout for the Preschool room, library, art, and reception area.
  11. Arlyn, Mrs. Christy, Dave and Mrs. Shedd are quickly packing for their temporary move.  They will be in temporary spaces for 3 weeks to allow the construction to move forward a little earlier.



HALLWAY

BRICK AND NEW WINDOWS 
                                                                  IN THE LIBRARY

WORKING ON SIDE WALKS



Soon we will be looking at:



THANKYOU FOR YOUR SUPPORT AND UNDERSTANDING DURING CONSTRUCTION!


IF YOU HAVE ANY QUESTIONS PLEASE CALL ALICIA OR FLOR.