Wednesday, May 7, 2014



Everything is going at the same time to get phase III done by May 23!!!

  1. Side walk near the parking lot is getting done this week.
  2. Bathrooms near gym are getting tile today!
  3. All the marmoleum floors are going in.
  4. Final paint colors are in and the new administration area is all painted.
  5. Tile in the new Health bathroom and painting is happening.
  6. Cafeteria cloud ceiling is done.
  7. So many things happening and it is looking great!!

sidewalk by the parking lot

administration
library

Wednesday, April 30, 2014

Update




  1. Kitchen hood is in and the tile is in the kitchen!  Beautiful new quarry tile is in and ready to get grout.
  2. They are installing marmoleum in the server room and will start the cafeteria room this week.  We are going to heat a little the 1965 wing to make sure we keep the area at 55 F to satisfy our flooring warranty.
  3. Library Addition is framed and insulated.
  4. They continue to paint and work on the ceilings.
  5. Side walks are starting to go in and the south egress path is on the beginning stages.
  6. Time is of essence and the clock is running for our move on May 23!!



We had a great Oversight Committee Meeting today and had a walk through the construction.

We continue to work on the Pond issue and make sure we keep updating our Capital plan as we get owners manuals from the Contractor.

Thank you for all your time for the Committee!

Rob Chickering, Albert Petrella, Alice Angeny, Mike Duane, Alicia Lyford and Bill Ford



If you have any questions don't hesitate to call or email,
Alica alyford@u32.org
Flor diazsmith.flor@gmail.com

thank you for your support!



Respectfully

Flor


Wednesday, April 23, 2014

Update April 23,2014







They are full guns out in the addition! (Contractor language!)
First coat of paint in the new offices, library and cafeteria.
They are working on the library addition floors now and the entry way recess matt slabs.
The Stage Curtain was hanged yesterday.
We did some testing on the temporary parking area today, were we have some heaving from frost.
We continue to work on the final update for the Fire Water Pond.
The new kitchen equipment is on site.
The new marmoleum flooring will start to be installed this week.
The Structural engineer came to review the structure in Phase III and he was happy with everything.
The Beam bearing was reviewed and he will send us a site visit report.








New cafeteria

glass windows from hallway tto cafeteria




New Skylight!

look who is supervising the job after school!

 cafeteria with the new green and mayan gold on the walls!
looking at the time capsule, it will be on the library side wall as you enter the building.

sketches on site to install the metal box for the time capsule



Thank you Wright and Morrisey and Truex Cullins for all your hard work!!
Thank you Bill Ford too!


Thank you to you East Montpelier for your support and your patience!!

Monday, April 7, 2014

UPDATE



Wright and Morrissey has accepted the early substantial completion on Phase III on May 23, 2024!!
EMES Staff affected by this move will vacate the six classrooms on the West end of the 1965 addition. Asbestos abatement will start of May 27, 2014 for no more that 10 days.

On the site they are done installing new windows on the Phase III section.  They continue to finalize the roofing in the 1965 part of the School and they are busy finalizing the library framing and roof structure.
The New Cafeteria is all framed and closed in.  Plumbing inspection is done and now they are finalizing electrical, blocking and in some areas they are putting up the Sheet Rock!!  It is moving along fast and on schedule!!

Getting in an out of the drop off circle and parking is still hard so we appreciate your patience and remember it is temporary.   Most kids have taken a tour of the building and are enjoying seeing the progress.

The Oversight Committee is meeting twice a month every other Wednesday at 8:30 am and the main goal of the Committee is to make sure more people can be informed of the progress and can share with their neighbors and friends.  The Committee is also working on the Capital Plan with Todd's input.

If you have any questions please don't hesitate to post them in this blog, email diazsmith.flor@gmail.com or Alyford@U32.org or call the School.

Wednesday, March 12, 2014

Update




Construction and renovation continues in the 1965 portion of the building.  We have 3 months left for this phase to be finished!! and then we will start Phase 4.

-Structural Steel is in.
-Block infill and sheet rock infills are being worked out in the      most creative way we can. 
-Brunel Roofing has started roofing the kitchen and new cafeteria.
-All demo in kitchen is done and new plumbing and trenches in the exiting slab have been taken care of. Kitchen infill in slab and new slab will be pour tomorrow.
-Andy Shapiro is on site today checking air Leakage.  
-Sprinkler for this area has been rough in to.

The good news is the paint issue in the gym has been resolved!  The gym had a lot of work done over vacation and it is re-painted now.  Here are some pictures of them striping the paint and prepping for the new paint.






PLEASE EMAIL US IF YOU HAVE ANY QUESTIONS

diazsmith.flor@gmail.com

Friday, February 28, 2014


See you at Pre-Town Meeting at U32 tomorrow!
9:30 am



Facilities Report
The EMES Renovation and Expansion project recently entered Phase III!  It is hard to believe that a year ago we were thanking you for passing the bond and hoping to go out to Bid.  Final plans were submitted by TruexCullins last spring, and Wright and Morrissey was awarded the bid in June, 2013. 
At this point in the project we are on budget and on schedule.  We owe a huge thank-you to Wright and Morrissey, TruexCullins Architects, our Clerk of the Works, and support from the EMES and WCSU Staff and Administration.
A recap of Phases I and II (June 24th, 2013 - December 22, 2013):
·      Preliminary site work to improve drainage around the entire building and existing parking lot; prep work on the temporary parking spaces, and adding an additional parent drop-off loop and bus loop in the front of the building.
·      Renovations to the existing Gym, which included new bleachers, a new floor, asbestos removal, new bench areas, acoustic panels, mechanical, lighting, and a PE storage area. 
·      The majority of Phase II was devoted to the South addition.  This addition included two new classrooms, a new Music and Art room, Bathrooms, Tutoring Space, and a Language Room. 
Plans for Phase III (December 2013-June 23,2014):
·      The existing music room down to the K/1 exit, near the short term parking, relocated to the new wing over the December break.  Construction in the new library, the pre-k classroom, and the “admin suite,” which includes guidance, health, occupational therapy, a conference room, staff room, and the principals’ office, will take place over the winter and spring of 2014. 
·      The kitchen and new cafeteria will be built in the latter part of Phase III.  This work will also include the asbestos abatement in the kitchen, which will happen during the February school Break.  (NOTE:  Town Meeting will be at U32 this year.)
Plans for Phase IV (June 2014 – August 2014):
·      The contractors will complete the site work that began in Phases II and III, as well as all other work in the existing building.  The renovation of the last section of the 1965 wing, as well as the 1989 wing will happen during these last few months.   This will include heating, mechanical, new windows, insulation, lighting fixtures, new built-ins and more.   The existing library will become two primary classrooms, and the existing bathrooms will be renovated.  This work will be completed by August 2014.
There are two life-safety requirements that we will need to comply with: a Fire Pond and a South exit egress path that were not part of our original budget.  We will continue to work on the details of these requirements, ensuring the Board has all the information before final decisions are made.
We want to thank you for your continued support.  This project would never have been possible without the East Montpelier Community!  Thank you for caring about our school and advancing the next generation!
Respectfully,
Alicia Lyford and Flor Diaz Smith

Construction is moving quickly on Phase III

The kitchen is now close but do not worry breakfast and lunch will be served at school!!  Please visit the school webpage for the lunch menu in March.

Activities at School this week:

Kitchen asbestos abetment is happening now during break.
All demo is done in the east section of the 1965 area of the school.  From the temporary parking look to the gym area.
Trenches for plumbing are now closed.
Interior framming is going in now.
No surprises in storm and sewer lines.
Roof might be going on by the end of the week.
Stripping paint in the gym to re-paint.